Ok, it's been a while since my last post, so here's a broad update:
1) Floors are done & painted. Probably will have to repaint sometime in the next two weeks, but that's mostly cosmetic at this point.
2) Walls, ceiling panels, and new LED fixtures are installed, painted, wired, and working!
3) Unpacking has begun, pictures, etc. hung and collectables displayed.
4) Portable A/C w/heat is on order - high humidity/heat here in Piedmont NC have limited my time in the shop.
5) Small refrig in sitting area isn't looking too promising - been sitting unplugged for almost 2 years, so probably refrig. has seeped out - will probably replace as repair costs aren't worth the expense.
6) Working on getting things arranged and to determine needed new LED worktable lamps (bar, not bulb type); will donate older bulb type lamps to ReStore.
So, as of this afternoon, here is the interior as well as my freshly painted front entrance:
Attachment:
Resized - Front Entrance_1.jpg [ 163.3 KiB | Viewed 1173 times ]
Attachment:
Resized Ceiling Completed_1.jpg [ 134.96 KiB | Viewed 1173 times ]
Attachment:
Resized Left Wall_1.jpg [ 164.25 KiB | Viewed 1173 times ]
Attachment:
Resized Right Wall_1.jpg [ 135.21 KiB | Viewed 1173 times ]
Attachment:
Resized Right Wall_1.jpg [ 135.21 KiB | Viewed 1173 times ]
The week ahead is mostly inside cleanup and unpacking, all predicated on the weather.